Hi ,

As per my client requirment , Mfg operations are performing in two diff plants , for example in Master recipe

Header material with plant 1

Operations 10 = Equipment 1 plant 1

Operations 20 = Equipment 2 plant 2

Operations 30 = Equiment 3 plant 1

while creationg master recipe , I'm not able to create operations with two diff plants.

could you please suggest me how to create MR with the above senario

sekhar

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Sekhar,

In case you want to implement cross-site span production, please refer to this [guide|https://websmp209.sap-ag.de/~sapdownload/011000358700001374792008E/site2site.pdf].

As alternate, you can try to implement your scenario by using Work Centers (rather than sites) for each plant.