on 03-29-2011 10:11 AM
Hi ,
As per my client requirment , Mfg operations are performing in two diff plants , for example in Master recipe
Header material with plant 1
Operations 10 = Equipment 1 plant 1
Operations 20 = Equipment 2 plant 2
Operations 30 = Equiment 3 plant 1
while creationg master recipe , I'm not able to create operations with two diff plants.
could you please suggest me how to create MR with the above senario
sekhar
Sekhar,
In case you want to implement cross-site span production, please refer to this [guide|https://websmp209.sap-ag.de/~sapdownload/011000358700001374792008E/site2site.pdf].
As alternate, you can try to implement your scenario by using Work Centers (rather than sites) for each plant.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.