on 03-28-2011 3:51 PM
Hi,
We are on PPM5.0, working with cProjects-PS integration.
Understand that the PS Profile for integration is CPR001.
How can we define another profile that links with cProjects?
Business requirement is to have a different profile.
Please advise.
Hi Deepak,
In your accounting system, please implement BADI: IAOM_BUSINESS_SCENAR
Then you can use method CHANGE_PROJECT_PROFILE in order to select the right PS profile.
BR
Matthias