on 03-28-2011 2:43 PM
Hi,
We are using procurement type "PReq + Reservation for WBS Element" and item category "L" for materials components.
Which should be the process to follow if once I've assigned a component to an activity I realize I've got stock in a storage location and I don't need to purchase it? How we are suppose to assign the components to the activity?
Thanks a lot
Hi,
You can keep the option of selecting either " Res+ PR for WBS" or "Reservation for WBS" while assigning the component instead of making Res + PR for WBS as default procurement type.In your thread you have mentioned that there are some materials whose stock exists in storage location, it means you are maintaining such materials in your inventory(plant stock) apart from your project specific procurement(project stock).
So once you find the material in stock do a stock transfer from the plant stock to the specific WBS element to issue ut against your reservation.
Regards
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You will have to MRP in order to check availability & raise PR for required quentity only.
we are using project specific MRP where create reservations for the requirement then all available materials are moved to project stioks & run MRP.
Regards,
SL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
1. You can make use of the Res/PR indicator. Set it to "From Release" for example. So when your activity is in CRTD stage, you can assign all your mat components as desired with the procurement indicator as "Reservation + PR" (supposing that you dont know the stock situation by now).
2. Get the stock details, cross check with your requirement manually & decide which are the mat components for which PR is required / not required.
3. Delete all the mat comp with the procurement indicator "Reservation +PR", for which actually PR is not required. Add them again with a procurement indicator "Only Reservation".
-- We may make use of the funtion "Material Availability Check" in this, but not sure of the total funtionality.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Try 412 Q movement type to transfer material from plant to project.
Create PR indicator for reservation and assign it in network profile if you want it as default reservation is to be selected or keep it blank in network profile then system will prompt pop up asking to select the required indicator.
regards,
Hi,
Procurement Indicator "WE" is perfect
We tried movement type 412Q but it doesn't work.
We also tried using MB23 tcode to make the picking (movement type 281), it assigns the actual cost it doesn't appears as project stock as we want.
Edited by: mforman on Apr 6, 2011 2:54 PM
Edited by: mforman on Apr 6, 2011 3:00 PM
User | Count |
---|---|
92 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.