on 03-28-2011 2:06 PM
Hi PS experts,
Can you tell me if it is possible to budget on a year-period level?
I'm not an expert on PS, I've used CJ30 to set up a budget and I can't find a possibility to select a year and drilldown to period level.
I want to use a project for PM budget activity control, the PM budget is set up on a monthly base.
What options are available?
Kind regards,
Johan
I'm neither an expert, but I think is not possible. Have a look on Budget Profile (Tcode OPS9)
You could use monthly budget releases in order to control it month by month (Tcode CJ32)
Regards