Dear experts,
i have a problem when i am going to do Collective confirmation in CN27 the factory calender which i use in the project (00) does not come, system use another factory calender with confirmation (MD)
i have checked the factory calender assigned to project definition and WBS and it is (00)
How can i solve this problem ?
Check the fact cal on the work centre assigned to the activity you are confirming or the plant fact cal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank you for your help
i found that fac cal in plant is different
thank you