on 03-25-2011 6:00 AM
Dear Sir,
We are using PPDS for finite capacity based Scheduling of production orders . We have a scenario say a Production Order having 4 differnt sequential operations and operation no 3 has partial confirm status and all operation 1 ,2,4 have released status .
We are now doing the re-scheduling . Kindly let us know can this order now be re-scheduled (as it has operation no 3 in partial confirm status ) .
Kindly help us pl .
Regards
Sonia Agarwal
Hello Sonia,
you have to interrupt the partially confirmed operation, then it will be possible to do a rescheduling. Interrupting an operation can easyly be done in the DS-planning board.
Best regards
Thomas