Re-Scheduling of Order having Partial Confirmed operation status

Former Member
0 Kudos

Dear Sir,

We are using PPDS for finite capacity based Scheduling of production orders . We have a scenario say a Production Order having 4 differnt sequential operations and operation no 3 has partial confirm status and all operation 1 ,2,4 have released status .

We are now doing the re-scheduling . Kindly let us know can this order now be re-scheduled (as it has operation no 3 in partial confirm status ) .

Kindly help us pl .

Regards

Sonia Agarwal

Accepted Solutions (1)

Accepted Solutions (1)

former_member583456
Active Participant
0 Kudos

Hello Sonia,

you have to interrupt the partially confirmed operation, then it will be possible to do a rescheduling. Interrupting an operation can easyly be done in the DS-planning board.

Best regards

Thomas