Hi all

My client want rescheduling( pro rata basis) for partial confirmed activities. and their sucessor activities. Pls any body tell me whether this standard features available.

Eg Act10 having 10 days duration . i will confirm 20% on 5th day. Then im delay of 3 days against planned and also during scheduling Act 10 Earliest finish date has to increase 03days.( 10+03=13)

Regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

there is a functionality called forecast scheduling in PS.

please read sap help on forecast scheduling and post further queries..