Hi all SD Gurus,

I have two materials A and B I want B to be replaced when the stock for A is over.

Edited by: sagar7uict on Mar 22, 2011 9:01 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

u can use vb11 to create material determination records.

and in SPRO in sd basic functions make the appropriate settings.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

You can do the Material determination configuration setting through the navigation path given below:

IMG -> Sales and Distribution -> Basic Functions -> Material Determination -> Maintain prerequisites for material determination.

Then create condition record, for that goto TCODE : VB11

Enter the proposed reason,Material Entered as A and Material as B.

Save the condition record.

After this configuration,once material A in stock is over,material B will be replaced.

With Thanks and Regards,

Priya.