Planned orders are created when Production order is open

Former Member
0 Kudos

Hi Everyone

We have Make order and Make to stock scenarios in the system for various products. When Production order is still open ( Fully confirmed with C015 and partially delivered), system assuming that order is completed and created a new planned order for the undelivered quantity against Sales order.

As per my knowledge MRP shouldn't create new planned orders when old production order is still incomplete. The old production order has status REL, PDLV and CNF.

Any help is appreciate and it is our production issue

Regards

Prasad

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

is the order marked as completely delivered on the Warehouse view? Have you reached the under delivery tolerance for this order with your partial delivery from production? If yes, this would be the reason why the system thinks that a new order is required

Regards

Thomas