Dear All,
User has selected wrong project profile.
I need to know what are the implications or impact of wrong project profile on the open project.
Thanks
PM
Hello,
Project Profile shows the behavior of the project. It contains basic settings related to Organization structure, Planning, Settlement, and various profiles which contains different settings.
so this is very important and critical field in Project. So you have to check setting in that profile and compare to correct one.
Thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Project profile is what controls most of the attributes of your project. Match both the project profiles i.e the wrong one that is used and the correct that should have been used. You will be able to understand the difference as well as the impact easily.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
is it totally different type of project.. then it will make a lot of difference..
if the difference is minimum for example only org. structure difference then may be you can manually edit it..
another most important thing is the numbering.. most of the user will get confused with wrong numbering of project...due to wrong profile...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.