Hi :

I encountered very strange case,in item level of sales order, then I went to schedule line tab and saw confirmed qty showed grey and zero, but in md04 and mmbe the available qty is 10,then I went back to header level to click on ATP check, it only shows one button "continue", and at bottom, I saw "Dely proposal:not possible" which means I am unable to confirm ,please help.

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi sure:

Since the plant where this material be shipped to is none-planing plant, then we need to change the MRP type from PD to ND, then go back to va02, then go to procurement tab of header, then delete plant and schedule line category and let system refresh since it needs to be generated new schedule line category, once it gets refesh, then I clicked ATP, then click completed delivery, then it got confirmed, hope you guys can learn sth from it, good luck!

dilorenzo
Participant
0 Kudos

This message was moderated.

Former Member
0 Kudos

It was solved my our internal consultant.

Lakshmipathi
Active Contributor
0 Kudos

Why dont you share how it has been addressed ????

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

Go to

IMG >> SD >> Basic function >> Availability check and TOR >> Availability check >> Availability check with ATP logic >> Define default settings >> Maintain E in front of your sales area

Then in sales order u will able to see all tabs

One time delivery

complete delivery

delivery proposal

ATP qty.

scope of check

other plant

Kapil

Former Member
0 Kudos

But I am still unable to confirm...confirm qty still shows zero although I check ATP again...help.

Former Member
0 Kudos

Hi I had checked it in vov6, it had been ticked for availability.

Former Member
0 Kudos

Hi:

a) Ensure that your schedule line category is ticked for "Availability"

It is CP, what did you mean for tick for "Availability"?

b) Ensure that in MD04, no delivery reference is flowing for that material

in Md04 i am unable to see this sales order, so no delivery rference.

Lakshmipathi
Active Contributor
0 Kudos
what did you mean for tick for "Availability"?

In VOV6, for CP, you can see a field Availability which should have been ticked.

thanks

G. Lakshmipathi

Lakshmipathi
Active Contributor
0 Kudos

Couple of things you need to check

a) Ensure that your schedule line category is ticked for "Availability"

b) Ensure that in MD04, no delivery reference is flowing for that material