No Commitment in report If I create manual PR with account assignment N

ashutosh_saraf
Participant
0 Kudos

Dear Experts,

I created a manual PR with account assignment N, But Commitment for that Network activity associated to particular WBS is not showing in the report.Can anybody put some valuable effort to resolve my query, with necessary configuration required for that.

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If you used same material Number & same project with Network activity to create PR through project, is it working fine & record on all reports correctly??

Regards,

Sam L.

ashutosh_saraf
Participant
0 Kudos

Yes its working while creating PR from activity

Former Member
0 Kudos

Hi,

Note 152571 , see whether its usefull..

Regards,

Sam L.

Former Member
0 Kudos

Hi,

Are there two different GL accounts in this scenario OR the same GL account ?

regards

Former Member
0 Kudos

Hi

Check for two things

1. If the committment management is active for project system in the controlling area settings (OKKP)

2. if the G/L account used is created as a cost element in cost element accounting and is also valid as of the date when the PR is being created.

Hope this is helpful....

Regards

Kaashif M

ashutosh_saraf
Participant
0 Kudos

Dear Friend,

I have activated the commitment in OKKP.GL is also associated to Cost element.Kindly Advice with valuable solution.

Regards

ashutosh_saraf
Participant
0 Kudos

Thanks , Query resolved

former_member230675
Active Contributor
0 Kudos

If possible please mention the result (how did you solve it), as it will be useful for all of us.

ashutosh_saraf
Participant
0 Kudos

Activated Commitment in OKKP and Assined GL to cost element and raised PR.