Dear Experts,
I created a manual PR with account assignment N, But Commitment for that Network activity associated to particular WBS is not showing in the report.Can anybody put some valuable effort to resolve my query, with necessary configuration required for that.
Regards
Hi,
If you used same material Number & same project with Network activity to create PR through project, is it working fine & record on all reports correctly??
Regards,
Sam L.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check for two things
1. If the committment management is active for project system in the controlling area settings (OKKP)
2. if the G/L account used is created as a cost element in cost element accounting and is also valid as of the date when the PR is being created.
Hope this is helpful....
Regards
Kaashif M