Central contracts:
Scenario:
1. Contract is created --> Released --> Distributed to backend successfully
2. Price change on a line item
3. Buyer changes the contract line
4. Release the contract
Is this possible? any limitations thanks
Yes netahaj
this time NEW CONTRACT VERSION WILL BE CREATED and again you have to distribute again and recent updated info reached ECC system
Muthuraman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
IF the price is changed the Contract will be subjected to relase and once released it can be successully diributed to backends, I do not think there is any limitation around this.
with regards
Manjunath