on 03-19-2011 7:17 AM
In my project i am using backward scheduling ,before going for scheduling i am delete the basic start date of project and network header .then i go to planning board and carrying scheduling now system is give me a popup "start date ".than i maintain the start date and carry the scheduling , in the backward scheduling starting is not required and system is determine starting date also , why system is asking starting date please let me know any configuration changes in Planing board or scheduling parameter.
Regards
Rao
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
I try with the network determines dates but it's ask the start date ,please suggest me . but in the planning board "options " i am select the scheduling in that scheduling parameters per activities scheduling type is shows as a forward scheduling but it's shows as hide
Regards
Rao
Edited by: bhavanio rao on Mar 21, 2011 5:48 PM
can you explain the settings in OPU6..
Value maintained for start in the past..?
Please also check the Parameters for WBS scheduling..
Are you maintained Scheduling type same for both..?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Abdul ,
In opu6 in maintain starting in past 999
and opu6 configurations
adjust basic date -2
scheduling type -backward
start in past -999
and check automatic scheduling,latest staging date
in the control parameter for wbs scheduling also
scheduling type -backward
starting date -999
scheduling method -wbs determine dates
and check-adjust basis date
Regards
Rao