Dear experts,
what should i do "set up & tranactions" so that i can apply the overheads costs on my project
i am in oil & gas company and they r using the Project System module just to manage the CAPEX costs/budget of the concessions, so the project is comprises only WBS elements without networks & activities
i created the project, budgeted, released and post actual costs "GR for materials" to the project
when i run the transaction CJI3 i found only the actual costs without the overheads... WHY??
Note: there is no project stock
i assigned a costing sheet & overhead key to the WBS elements
Hi,
Execute "CJ44" for the WBSE in question & then cross check CJI3.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Overhead Calculation is based on Costing sheet you maintained.
Calculation of overhead is done using the Base you define. So, when you run overhead calculation cj44 it will pick the cost element you maintained in costing sheet base for calculation of overhead.
so check your costing sheet configuration before you run overhead calculation.