Project Overheads

Former Member
0 Kudos

Dear experts,

what should i do "set up & tranactions" so that i can apply the overheads costs on my project

i am in oil & gas company and they r using the Project System module just to manage the CAPEX costs/budget of the concessions, so the project is comprises only WBS elements without networks & activities

i created the project, budgeted, released and post actual costs "GR for materials" to the project

when i run the transaction CJI3 i found only the actual costs without the overheads... WHY??

Note: there is no project stock

i assigned a costing sheet & overhead key to the WBS elements

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Execute "CJ44" for the WBSE in question & then cross check CJI3.

regards

Former Member
0 Kudos

Hi

i run the transaction and i got a messages say that Overhead Calculated

but when i checked the Actual Costs CJI3, i found nothing new "no overhead values"

Former Member
0 Kudos

Overhead Calculation is based on Costing sheet you maintained.

Calculation of overhead is done using the Base you define. So, when you run overhead calculation cj44 it will pick the cost element you maintained in costing sheet base for calculation of overhead.

so check your costing sheet configuration before you run overhead calculation.

Former Member
0 Kudos

The best thing here would be to get in touch with your FICO guy and ask him to check the Costing Sheet setup. I strongly feel that your issue lies in the costing sheet setup.