Cost Center Plan/Actual/Commitment

Former Member
0 Kudos

Hi

Want to Devlop a customized report for Cost Center where I need to display Plan/Actual/Commitments vaues for a cost center fiscal Year per period year wise.

Let me know which, tables I can use to get these values as COSS and COSP not shows values Period wise.

regards,

Atul Rajmane

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, in GRR1 you can use library 1VK

Former Member
0 Kudos

use 1vk and then use charatristices like period/year and value type for the desired output.

Former Member
0 Kudos

check RPSCO table

Former Member
0 Kudos

Hi,

I am able to get required the data from COSS and COSP tabel.

While going through COSS-OBJNR number I am getting my required cost center have Object number as KLZPG1F010000105CR0021 where ZPG is my Controlling area and 1F010000105 is a cost center.

But, I unable to get it meaning of KL and CR0021 in this string.

Let me know what it means so that I can form my object as required above to get deatils from COSS table.

regards,

Atul Rajmane

Former Member
0 Kudos

Hi,

KL-cost center(posted) used with activity type

CR0021-activity type

Former Member
0 Kudos

As far as i know object numbers are system derived numbers (internally numbered for particular objects by the system). For eg. Object numbers for WBS starts with PR followed by numerals.