on 03-15-2011 5:25 AM
Hi All,
I have created a Local PO in SRM and entered the supplier also.
When i logged on to the portal as supplier and click on PO response, in drop down list i can able to see 3 options as create manually / confirm completely & Reject completely, but all were disabled.
How to enabled them ?
Regds,
CB
Hi
go to the Business partner in the SRM Administartion tab 9n SRM 7.0 and click SRM Adminstrations
check the for the vendor --->supplier data tab
Check Purchase order response expected tickmark is there
No need of any settingsI
f you want to use Purchase order Response(POR) for the purchase order,
the Purchase order should have OR_IND flag on. If you don't have this
indicator set in PO, the response button in POWL will be grayed out.
Go to table : BBP_PDPSET .Enter the guid ID of the Purchase order
check the for the Field OR_IND
whether X mark is there
Regards
G.Ganesh Kumar