What Date in CNS0 we need to enter in Planned Gds mvm tab under general dat

Former Member
0 Kudos

Hi PS Guruu2019s,

Date should be after the (MRP2 tab in Material master Planned Delivery (Calendar day) + GR Processing Time (Working days))

Example:-

For materials A from Materials master days are two.

Thant means 16u2019Th March (consd'g 14'th march) we can enter data in CNS0 as in Planned Gds mvm tab under general data tab

Please correct me if I am wrong.

Many Thanks

MM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

>

> in CNS0 as in Planned Gds mvm tab under general data tab

> Many Thanks

> MM

The date of goods movement or delivery date of your items to the project site or to the client.

Former Member
0 Kudos

Thanks.

Issue solved