cancel
Showing results for 
Search instead for 
Did you mean: 

Safety stock caluculation

Former Member
0 Kudos

Hi

The issue is even though I have suffiecient stock still PRs are generating.I want to know why this PRs are generating.

I suspect this is because of safety stock.I have maintained Safety Days' Supply 22,Safety Stock Method SM (Max.of Safety Stock and Safety Days'Sup.from Loc.Prod.Master).

Please let me know how this safety stock caluculation works.

R

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

R,

Rather than explain, let me just say that if it is your goal to have PRs never exceed requirements, then you should not maintain anything in Safety stock at all. That is the whole purpose of Safety stock, to generate extra proposals to meet a particular business requirement.

Best Regards,

DB49