MRP Area in consumpion based planning

Former Member
0 Kudos

hi,

can anyone tell me how to run MRP automatically for a MRP AREA once Stock level comes below Reorder point .

Please suggest me on this.

Regards,

Sowmya

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Sowmya

In most shops, there are at least one or more materials every day which fall below reorder point. It is therefore more common approach to run MRP 'periodically' (e.g., once a day, or once a week, or once a month) using Net change. Under these circumstances, only the materials which have planning file entries actually have MRP executed against them. As you probably know, any material which falls below reorder point automatically generates a planning file entry, and therefore becomes eligible for a net change mrp run.

Best Regards,

DB49

Former Member
0 Kudos

hi,

can u elaborate on this full cycle how to run . Please

Regards,

Sowmya

Edited by: sowmyavishwanath on Mar 14, 2011 6:37 AM

Former Member
0 Kudos

Sowmya,

Not much to tell.

1. Assign appropriate Materials to appropriate MRP area.

2. Assign VB (or similar) MRP type to appropriate Materials. Enter the appropriate reorder point in each Material master.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d256344af11d182b40000e829fbfe/frameset.htm

2. Schedule MRP to run every night, or at a frequency that meets your business requirements. Select Net Change, select the MRP areas that meet your requirements.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d2da044af11d182b40000e829fbfe/frameset.htm

http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d2e2244af11d182b40000e829fbfe/frameset.htm

3. Process new purchase reqs after MRP run. The only reqs you will get will be against materials where the onhand-stock-plus-firmed-receipts fall below the Reorder point you set in the Material master.

Best Regards,