on 03-10-2011 2:43 PM
We are on PPM5.0.
We plan to use subprojects in cProjects which meets a requirement that we have. We are now required to have this entire set (the main project with subproject) to be replicated under one WBS in PS. Is this possible? How?
We may be required to use a few subprojects, and one subproject may be linked to another subproject. And the business needs the entire set up to replicate under one WBS in PS (when "Flagged for Transfer").
Please advise.
Hi Deepak,
that's not possible by standard means. The automatic MLC scnearios always work for one project w/o subprojects. I think it could be developed / enhanced, but you will need someone with good technical skills in MLC
Best regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
7 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.