Hello Experts,
We have created a WBS element in one of the projects.
As per standard process, when we create the WBS Element the Asset under construction is also getting created through the settlement rule within the WBS.
These assets should have the same Cost Center as the WBS has. However we are in a situation wherein the Cost Center in the asset under construction is different than the Cost Center in the WBS.
I have checked the settings like automatic account assignment, etc but all settings look correct.
Can you please explain first what could be the reason for such a difference between Cost Centers in WBS and AuC's and what is the solution to avoid it in future?
Thanks in advance
Leena
Hi, could be CC copied from Invest program ID which assigned to WBS element
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the layout of the WBS element request cc field was kept hidden which is why it picked up incorrect CC maintained in that field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please try to use validation or substitution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.