Hello Experts!
During the release of cProject when the PS project definition is created I need to also autmaticaly link the WBS elements to cProject phases. As I understand this can be done by implementing DPR_FIN_GECCO_MANUAL BAdI. I implemented this BAdI, but I don't understand when is this BAdI is called.
Does anyone know when is this BAdI called or had a similar task?
Hi Misha,
the BAdi only works for manual MLC. It is only called when you press the corresponding button on the accounting tab. Best regards
Thorsten