on 03-09-2011 6:54 AM
Hi,
I need to have the Basic Start and Finish dates fields of the WBS elements in the CN60 Transaction. How to get the the dates fields?
Regards
In the data element for the field tick the change doc box to activate this to appear in CN60
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try using the dates field in the User fields tab. Make these fields mandatory. Any changes done to these fields will reflect in CN60. Alternatively you can discuss with your ABAPer if it is possible to populate these fields with the dates in Basic Start and Basic Finish fields maintianed in the Dates tab. Any changes done here will subsequently get populated in the dates filed in the user fields tab and will reflect in CN60.
This is just a guess. Give it a try and revert.
Regards,
Gokul
i think CN60 doesn't bring in the dates as default. You may use the date feild on the user's feild to capture any changes in the basic dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.