Dear Friend's,
Can is it possible to make procurement indicator field mandatory while planning material in project builder at material component overview screen.Because i have to enter 3 different procurement indicator's. (PReq + Reservation for WBS Element / Reservation for WBS Element / Reservation for plant stock)
Also i have checked in config. for Define Field Selection for components (Tcodes - OIPSMDMAT / OIPSMKMAT). There is no such field available.
Thanks & Regards,
Sandeep Theurkar
do not maintain any procurement indicator in the network profile system will ask you to maintain one while doing material planning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul,
Thanx.
I have not maintained procurement indicator in network profile, but it dosen't solve the problem.
While material planning in project builder I have to use 3 procurement indicators, here user can just by entering item category L system proceeds further and creates reservation for the network for any material. To avoid this i wanted procurement indicator field should be mandatory.
In Define Field Selection for Component you can have various fields, related to Detailed View for Materials & Material Overview except procurement indicator. So how I can make this field as a mandatory field.
Thanks & Regards,
Sandeep
Edited by: Sandeep Theurkar on Mar 9, 2011 6:11 PM
I may not be completely clear with your desired requirement, however I believe that you need to check your material component settings - how your material master in MRP4 view is defined to take individual/collective requirement , how is your procurement key (X, E or F) defined in MRP 2 view , strategy group, Mixed MRP in MRP 3 view , project definition settings - does your project allows project stock management (valuated or non-valuated) or BOM settings if used BOM transfer CN33. All these come in play together for a user to choose appropiate procurement type to be used for stock items (L) when assigning to an activity.
For example: Project definition if allowed for a valuated stock
- Reservation for network implies MRP 4 is marked u2018collective stocku2019 (2) / plant stock
- Reservation for network / Reservation for WBS together implies MRP 4 is marked u2013 u2018individual/collective stocku2019 ( )
- Reservation for WBS implies that MRP 4 is marked u2013 u2018individual stocku2019 (1)
Please let me know if of any help
Thanks,
Nakul
Edited by: Nakul Chakoo on Mar 14, 2011 9:33 AM
Hi Krisap,
I have checked by creating screen variant but not possible. Effect of this, system treats complete procurement indicator column as a mandatory.
For example i have planned 2 material with relevant procurement indicator. then below line items or rows are mandatory for the field procurement indicator.
Is there any other alternative?
Thanks & Regards,
Sandeep
Hi Sandeep,
Since procurement indicator helps to default frequently used combinations of settings in material planning... so may be you can default these settings as mandatory field in OIPSMDMAT and try...
I hope by this users will learn using proper procurement indicator...
(record cj20n in SDH0 is not that easy)
tnx.
Abdul