Hi All,

We are maintaining calendars on locations and occasionally we have to extend the timestream because the progress of time means that there is not enough time in the future for APO to work on.

When we want to set a none working day, we remove the date line completely from the timestream. Once you have removed a date line, you cannot click the FIX indicator to stop changes when you calculate the periods again to extend the timestream again.

How can we stop the "Calculate Periods" from adding in the date lines back in that we have removed for holidays when we need to extend the timestreams?

Mark

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Mark,

Base your timestream calendars on a Factory calendar. Maintain your holidays in the Factory calendar (SCAL, or pull your updated Factory calendar from ECC).

Best Regards,

DB49

Former Member
0 Kudos

Hi DB49,

Unfortunatly due to our arrangement its not an option for us to base it on the factory calendar in the ECC.

Mark

Former Member
0 Kudos

Mark,

You don't have to use an ECC calendar, you can create a factory calendar directly in SCM, and then assign it to a timestream.

Best Regards,