Dear gurus,
We have created initial stock for a material for date 01122010.
I can post goods for that date(01122010) for domesitic sales. Distribution channel =10:
I extend material for another distribution channel as 20 for export sales
But I am not able to post goods for distribution channel 20.
In customer order>scheduled lines>confirmed date is always 08032011.
How can I change this date as 011202010.
Regards,
Dear,
System calculate Delivery date From In-house production days which maintain in MRP 2 of material master.
Goto VA02 -- Shedule Line -- Click on Item availblity ( Ctrl + F5 ) or you can manually edit Delivery date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can change the date manually in the sales order.You can either do this at the Schedule line level or "requested delivery date' field.
Rgds
Sumanth.G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can change the date in the Schedule lines of the line item.
Regards,
Ramesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in sales order enter required delivery date as u want .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.