WBS Budget Report Writer GRR1

Former Member
0 Kudos

Hi Gurus,

I need to release a PS report with Budget Planned, Budget used (effective costs) and residual budget.

I need to write a report, but I don't know how to use CJE0.

I tried to use GRR1 Report Writer with 6* libraries, but I can't visualize budget planned.

I use CJ30 to plan budget, find it in BPJA table with 41 type but I can't use it in GRR1.

can you help me please?

Thanks

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

try using 12KST1A in CJE0 , does that not have what you want?

Former Member
0 Kudos

@Nicola.

I already Used this library and the report don't visualize the budget.

@Ankushkap

Did you know a simple way to export this report in Excel? I already know it but I can't find a good way to export in Excel (I wont create 5 files html and then open it with excel).

Thanks

Former Member
0 Kudos

Hi,

Make your report layout classical, Then you can trasfer it to excel.

BR

Anjali

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi G.,

use library 6P3 and on one column you select about Value Type = 41 or 42, so you can display original budget.

Nicola