Dear Experts,
I have already done cost planning.I want that cost planning shoud not be affected when i generate Purchase Requisition through Activity.Because if so happens then double cost is incurring as planned in WBS.
Regards
Hi,
As per my understanding, you are planning some cost manually along with activity planned cost. In this case it double the planned cost at the WBS level.
If you want to make it as original budget, copy it in the original budget and activate the budget availability control by releasing the budget. After, this it checks the budget.
Regards,
Punith.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How you are doing the cost planning?
Is it network costing..?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.