Dear Friends,
In Customization Define Procurement Indicators for Material Procurement
We have following option
1.PReq for Network
2.Third Party
3.Prelim. reqmnts
If i use use option 1.PReq for Network --> Costing Relevancy check box is active when we attache material for an activity in Project structure in turn it derives Planned cost for project.
In case of option 3.Prelim. reqmnts --> Costing Relevancy check box is NOT ACTIVE for material. Is there any setting we can activate it.
Note: We are not using BOM.
Thanks
>
> in Project structure in turn it derives Planned cost for project.
>
for Plan cost calculation refer OPSV as well
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Cost relevancy tick is not set anywhere. However it derives based on various paramteres like
1. Type of stock ( Valuated or non valuated)
2. Item categiry ( L or N )
3. Also the Material master setting for individual/collective indicator
BR
Anjali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.