NWDS Patch

Former Member
0 Kudos

Hi All,

I`m using NWDS 7.11 SP04 for developing BPM applications. But my CE server version is 7.11 SP01. For deploying BPM in CE server both NWDS & CE server should be in sync(ie.., Both shd be in same SP level). Hence i want to change the SP level of NWDS from SP04 to SP01. Is that possible..?Please help me out....!!

Thanks & Regards,

Arun.

Accepted Solutions (1)

Accepted Solutions (1)

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

Downgrading the component is not possible. Better you upgrade your CE to SP04.

Thanks

Sunny

Former Member
0 Kudos

Thanks sunny..!!

Former Member
0 Kudos

I have Upgrade my BPM conmponents alone to SP4 & its working fine.

Thanks,

Arun

Edited by: arunganesan on Mar 15, 2011 2:02 PM

Former Member
0 Kudos

List of components Upgraded to SP4:

BPEM-BUILDT

BPEM-CONTENT

BPEM-CORE

BPEM-FACADE

BPEM-FLEXUI

BPEM-HIM

BPEM-MON

BPEM-PP

BPEM-WDUI

Thanks,

Arun