Changing Profit Center in Partially Delevered Sales Order

Former Member
0 Kudos

Dear Experts,

Can anybody tell me how we can Change Profit Center in Partially Delivered Sales Order?. in Standard, System allows to change PC in open sales Order without any subsequent documents.

There is business requirement to change PC in all Open Sales Orders.

br,

vgl.

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Try this.

Go to MASS, Key in Object Type BUS2032, select Table MASSVBAP and click on "Fields". There select the field "MASSVBAP-PRCTR" and execute.

Next paste those open sale orders and again execute. There maintain the required Profit Center on top cell and click Carry out mass change.

thanks