factory calendar assignment

Hi Gurus,

Can anybody please exaplain me the following. We are now running our plant in terms of production process 7 days a week. All these days the the 5 day factory calendar was only assigned. Now the business is wanting to assign the 7 day factory calendar. Here are my questions and this calendar is only for 1 plant.

1) Is there a plaace specifically for each module where the calendaar gets assigned, like sperately for MM, PP etc. Or everything is the same?

2) Where do we assign the new calendar to the plant? Is it in the plant definition in config? or is there a separate place in config for PP modiule only. Please clarify this





If you are changing the factory calendar from 5 days to 7 days then there is no need to assigned it to any where. Once you do the changes in SCAL for particular calender it will reflect every where.

But if you are creating the new calendar in SCAL then you need to assign it to plant in OX10 'SM30 - V_T001W'. and all work center in CR02.shipping point and Sales org in SD,

Best option for you is change the existing factory calendar.

Please refer this link,

new factory calendar



1 View this answer in context