Hi All,

While uploading package using SAINT i am facing some errors. I am at phase CHECK_REQUIREMENTS and RUN_SPDD just completed, and getting the below message

"

button Repeat Skip Cust.Cockpit

"

"Phase CHECK_REQUIREMENTS: Explanation of Errors

Open Data Extraction Requests

The system has found a number of open data extraction requests. These

should be processed before starting the object import process, as

changes to DDIC structures could prevent data extraction requests from

being read after the import, thus causing them to terminate. You can

find more information about this problem in the SAP Notes 1081287,

1083709 and 328181.

Call the Customizing Cockpit data extraction transaction and process all

open extraction requests."

I want to stop the upload. Please let me know

1) CAN I Stop the upload at this phase.

2) Will there any implication on the sytem if i stop it

3) How to stop it

Please reply as i m stuck here now.

Regards

Accepted Solutions (1)

Accepted Solutions (1)

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

Check if you have pending BI queues in the system. You can stop here and clear all the queues then start again your patch application from the same point.

Thanks

Sunny

Answers (1)

Answers (1)

JPReyes
Active Contributor
0 Kudos

This question has been asked and answered in multiple occations.

Did you search before posting?... my guess is NO.

Read the "Rules of Engagement"

Regards

Juan