Hi All,

I have mainatined overall budget in Object Currency for one Project Definition.

In transaction currecy budget values appears same for Overall and Annual views but in Controlling area currency Overall Current Budget value is less than Annual yearwise current budget value. Could you please let me know why this is happening? Is there any setting issue?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Are you using Budget Release functionality as well?

Former Member
0 Kudos

Hi,

Thanks for your reply on this.

We are not using Budget Release functionality.

But how it is related to this issue?

Thanks

Former Member
0 Kudos

Release values may be different that overall budget values for repective periods.

Is it happeneing on all the Projects or one off?

It seems you are in the process of upgrade, so not sure if this is related to that.