Reg:Planned and Actual POC

0 Kudos

Hi,

I have one requirement in progress analysis that system can find out the date wise planned and actual POC e.g:-

A1 activity having ear start date -01.03.2011 fin date- 15.03.2011

A1 Actual date-01.03.2011 to 03.03.2011 processing =30%

But when i run CNE1 and putting To Period =march 2011 and then cne5 system is showing result month wise planned and actual poc.

My requirement is to get planned POC as per date .If i will select for 3 days then planned POC also comes for 3 days and not for 15 days(01-mar to 15-mar)

We want to use progress analysis for activity date only

Progress version-100

Planned method- Time Proportionality.

Actual Method-Degree of processing from confirmation

So when we confirmed the activity 30% then in actual POC it is showing 30 and in plan also for 3days(01.03.2011 to 03.03.2011).

With Regards

Rohit Prakash

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear Bhaskar,

I am having similar requirement, please post your observations

Regards,

Avinash

0 Kudos

Hi,

Thanks for reply Anjali

.Whether there is a way to see the planned POC and actual POC as per date we select.

Still i am waiting for some more experts opinion.

Former Member
0 Kudos

Hi,

Please read the following link

<Link deleted by moderator>

Hope this will help you

BR

Anjali

Edited by: Virendra Pal on Mar 3, 2011 12:34 PM

No spoon feeding please - Rohit should be able to search himself

Former Member
0 Kudos

Hi,

As per std sap, System always calculates plan values for the whole of the period between the planned start date and planned finish date.

BR

Anjali