Job Scheduling in Solution Manager - Error creating Periodic Job

Hi all,

I am in the process of testing the Job Scheduling functionality using the Solution Manager. I have setup the criteria manager, ec. in the satellite system, and done the config in Solman as well.

I am able to successfully setup up a 'on-time' job.

it's only when I try to setup a periodic job, I end up getting following error

Any thoughts? Is there any piece of config that's missing? All the SICF services needed for this functionality are running fine.

Thanks for the help.

*----


500 Internal Server Error

Error when processing your request

What has happened?

The URL https://fsspsm.target.com:/sap/bc/webdynpro/sap/wd_ags_ejr_job_req_gaf_app was not called due to an error.

Note

The following error text was processed in the system PSM : Message was not created

The error occurred on the application server fsspsmap01_PSM_00 and in the work process 1 .

The termination type was: ERROR_MESSAGE_STATE

The ABAP call stack was:

Function: BAPI_NOTIFICATION_CREATE of program SAPLDSWP_NOTIF

Method: MSG_SUBMIT of program CL_DSMOP_BSP_NOTI_MODEL=======CP

Method: SUBMIT_REQ_CRM_DATA of program CL_AGS_EJR_JOB_REQUEST_FACTORYCP

Method: SUBMIT of program CL_AGS_EJR_JOB_REQUEST_FACTORYCP

Method: PROCESS_SCENARIO_PERIODIC of program CL_AGS_EJR_JSM_PROC_STANDARD==CP

Method: PROCESS_JOB_SCENARIO of program CL_AGS_EJR_JSM_PROC_STANDARD==CP

Method: IF_AGS_EJR_JSM_PROC_FPM_CTRL~AFTER_PROCESS_EVENT of program CL_AGS_EJR_JSM_PROC_STANDARD==CP

Method: AFTER_PROCESS_EVENT of program /1BCWDY/K54G9RCMK7J4Z427H49S==CP

Method: IWCI_IF_FPM_APP_CONTROLLER~AFTER_PROCESS_EVENT of program /1BCWDY/K54G9RCMK7J4Z427H49S==CP

Method: CALL_UIBB_PROCESS_EVENT of program CL_FPM========================CP

*----