Hi!

I have to substitute a func.area in CJ20N in WBS-element and in project definition.

In standart substitutions I maintained a subst. for WBS-element and for project definition. But func. area is changed just in WBS-element.

How can I substitute func. area in project definition?

thank you

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

Hi

Did you maintain substitution for both PD and WBS in OPSA, and also did you checked the automatic substitution.

Pls also try in CJ20N > Edit > Validation / Substitution > Substitution and check whether any message is there.

Tnx.

Abdul

Former Member
0 Kudos

Hi, Abdul!

Thanks, in OPSA substitution was maintained just for WBS

Now it's ok

former_member230675
Active Contributor
0 Kudos

thanks for the info. hope u can close it now.

Former Member
0 Kudos

yes, thank's