cancel
Showing results for 
Search instead for 
Did you mean: 

DIP - 1 Day equal to 24 Hours of Work

fortian
Active Contributor
0 Kudos

Hi,

I've created a DIP which use Cost Elements as Characteristic.

The problem is that in the internal activities, if I set as work unit 'D' (Days) it takes 24 hours for each day as original quantity.

I want to take only 8 hours for each day, as I've set on the Work Center capacity.

How may I change it?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

Go to Txn CUNI for dimension TIME and unit DAY and change the numerator to 8 hrs in seconds

Note - changing unit applies to the whole system and is hence not recommended - but you can create a new unit and do it that way

fortian
Active Contributor
0 Kudos

Thanks Virendra Pal,

I was expecting another kind of solution. Cause I think I won't assume the risk of modifying these parameters, as they might affect to other processes.

Thanks.