Hi,
I've created a DIP which use Cost Elements as Characteristic.
The problem is that in the internal activities, if I set as work unit 'D' (Days) it takes 24 hours for each day as original quantity.
I want to take only 8 hours for each day, as I've set on the Work Center capacity.
How may I change it?
Thanks
Go to Txn CUNI for dimension TIME and unit DAY and change the numerator to 8 hrs in seconds
Note - changing unit applies to the whole system and is hence not recommended - but you can create a new unit and do it that way