Dear Expert ,

I'm working with Requirement strategy 11 in R3 , what's the equivalent strategy in APO ? Or how i can work with gross requirement in SCM APO

Regards

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member614205
Active Participant
0 Kudos

Hi,

the strategy 11 is not integrated into APO. strategy 11 is as 10 without consideration of stocks. Workaround is not to integrated the stocks or filter out the stocks in the heuristic using BADI /SAPAPO/RRP_PLANNING, so that they are not considered.

Kind Regards,

Suneet