on 02-26-2011 9:12 AM
Hi
Below is the demand situation
day req/ recipt qty
1 -10
2 -10
3 -10
7 30 production order
8 -10
After SNP Run
day req/ recipt qty
1 -10
2 -10
3 -10
3 30 SNP planned order
7 30 production order
8 -10
Now in the above case it has planned 20 extra qty in total. Can we make it consider the production order first before it creates new planned orders.
Regards
Abhishek
Edited by: Abhishek Rai on Feb 26, 2011 12:16 PM
Hi Abhishek,
You include the production order category(s) (AC / AD) in the ATD receipt category group of the location and then run heuristic.
regards
Venkat DR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
any one?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The way it has been mentioned , check for pegging and also see if the reduntant planned order has been created by Heuristic or manually.If it is a manual creation , then you know the answer and if it is created by SNP , then it might be that Heuristic has created as required and there is some other planning engine also running, which is picking some cost or priority factors and creating again
Thanks