on 02-25-2011 10:02 AM
Hi ,
We have a requirement to track the changes in inspection plan (task list type "Q").
Details of requirement :
1) At creation and change of inspection, version of inspection plan should be maintained.
2) One version or change no. can only be used once.
3) System should not allow change in inspection plan which entering the version or change no.
Note ,we dont have requirement of release stratergy or workflow in our business requirement.
Please let me know what is the simplest way of implementation this requirement. I am working
with change no. for the first time, hence request you to eloborate the solution in detail.
Thanks in advance.
Regards
AA
Steps are -
1. Config to make change number mandatory
spro -> QM >Q .planning>General -->Define field selection
For task list overview
make field PLKOD-AENNR mandatory for task list type Q
2. CC01 - to create change master
Assign validity dates & task list group #
3. QP02 - Change inspection plan with this change number
4. CC02 - Set change number status to in-active to prevent change number re-use.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.