on 02-25-2011 3:48 AM
I have assigned shipping point to the plant loading group and shipping condition.But shipping point not determined in the sales order.While creating sales order i am getting a warning message that the document item 10 is not assigned a checking group.But in the material master checking group has assigned.Kindly help.
Dear,
Pls check following Master data is maintained or not,
1.Shipping Condition in CUSTOMER MASTER DATA.
2.Loading Group to Material Master and
3.PLANT for Line Item in Sales order
And in Config,
LOGISTIC EXCUTION>SHIPPING>BASIC SHIPPING FUNCTION>SHIPPING POINT DETERMINATION>ASSIGN SHIPPING POINT
and maintain following SC(shipping condition u maintained in CUSTOMER MASTER DATA)LGrp(loading group maintained in Material Master) and Plant and SHIPPINH POINT.
Rgds,
Ajit K Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Shipping conditions can be maintained in 3 areas.
customer master of SP
Sales document header
CUStomer material Info record.
If maintained in all the areas, system gives priority to CMIR
else SP shipping condition is considered.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Shipping conditions can be maintained in 3 areas.
customer master of SP
Sales document header
CUStomer material Info record.
If maintained in all the areas, system gives priority to CMIR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the img all assignments have done for shipping point determination.A plant is determined inthe sales order in line item level.Can you tell me why i am getting a warning message that no checking group has been assinned to the document item10 while in the material master a checking group assigned to the mm record.When i am putting the storage location manually that time also i am getting the same error message.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to set your availability configs. from:
1- You need to maintain checking group for availability check maintained to material master from SD-basic functions-Availability Check and Transfer of Requirements-availability check-Availability Check with ATP Logic or Against Planning-Define Checking Groups Default Value.
2- you need to assign your checking group to checking rule from SD-basic functions-Availability Check and Transfer of Requirements-availability check-Availability Check with ATP Logic or Against Planning-Carry Out Control For Availability Check
Hope these will meet your requirement.
Regards,
Sinan
Can you tell me why i am getting a warning message that no checking group has assigned to the document item 10 even though i have assigned a checking group in the material master.Is it a enterprise structure problem.Also i have noticed that the storage location is also not determined in the sales order.Due to which i am not able to do the delivery.When i am assigning storage location manually i am getting the same warning that the document item 10 is not assigned a checking grup.What is the relation between checking group and the storage location.?Kindly give me some reasons why shipping point is not determined inthe sales order even thogh all the shipping point determination assignments have done in the IMG>
kidly help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no link between, storage location and checking group.
In standard process, storgae location will not determine in sales order, it will determine only in delivery.
check the below customizing
SPRO> Production > Sales & Operations Planning (SOP) > Master Data > Assignment of Validation Rules to Key Figures
>
Maintain Checking Groups for Availability Check.
Request you to pls reframe the question clearly.
Bcoz, there is NO relation b/w shipping point determination & checking group of Av check, if I am not wrong.
Rgds
Sumanth.G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.