Dear experts,

could you please advise me what to configure in order to disable returning project statuses from TECO to REL for specific company. Is it possible to solve this request via standard SAP configuration or it can be done only through user exist adjustment. I do not have much experience with PS so if you can guide me as much in detail as possible, it would be nice.

Thank you in advance.

Accepted Solutions (0)

Answers (4)

Answers (4)

0 Kudos

In CJ20N - Just follow the below path:

shubham_kiyawat
Participant
0 Kudos

Dear Abdul,

I think you have misunderstood the question, Marian wants not to undo TECO.

Dear Marian,

You can easily achieve this by making user status on WBS in OK02.

Make user status which is automatically set once the TECO is set.

Make status Revoke technical completion as Forbidden.

Hope this will help you.

Regards

Shubham

Edited by: Shubham Kiyawat on Feb 25, 2011 4:08 AM

Former Member
0 Kudos

Hi, you can do it via Status management. You can find some info about it in help.sap.com and in spro-Project System-Structures-Operative Structures-Work Breakdown Structure (WBS)-WBS User Status

or Controlling-Internal Orders-Order Master Data-Status Management

former_member230675
Active Contributor
0 Kudos

Hi,

Just to reverse the system status TECO no need any special settings, as it is standard behaviour.

Open project in CJ20N > Edit > Status > Complete Technically > Undo

If system is not allowing then there may be a user status control.

Please check the user status setting. Then reverse user status first in order to reverse TECO.

Tnx.