on 02-24-2011 2:18 PM
Dear's,
I need to make this scenario Applicable:-
I have demand in Distribution plant 2013 for product P-100
Two Production Plant 2011 & 2012 available to produce this Product P-100
Component 100-100 with planned delivery time 8 days for location 2011
Component 100-200 with planned delivery time 4 days for location 2012
I need CTM to choose the lowest planned delivery time
How i can make that ? procured from the vendor on time
Regards
Rami
hi,
Actually you want to prioritize the ssource of supply selection based on lead time.You can maintain the priority in T-lanes as per lead time.In this example for 2011-2013 T-lane maintain priority as 2 for the product.
And for the 2012-2013 T-lane maintain priority as 1 for the product.
Hope this will help.
regards,
kaushik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CTM may do that (consider lower lead time source). Try playing around with Supply Distribution in CTM profile
CTM Profile > supply distributioin > specific product locations to push.
Alternatively try and maintian a 100% quota for the lower planned delivery time and see what happens
I am guessing from my new found knowledge and not necessarily testing.
Regards,
Loknath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.