Hi Expert,

I created a new u201CStatus selection schemau201D to exclude the wbs in status closed from the massive execution of cost settlement (Transaction CJ8G).

Although the WBS have the same u201CProject Profileu201D and the same u201CWBS status profileu201D, the system takes into account only one u201CProject definitionu201D and excludes all others.

Could you help me, please?

Thanks and regards,

Laura

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

In case you are using a variant please check the projct range that you have specified in the variant. Also, if yuo are using dynamic selections please check if there is something that blocking other projcts from being considered.

Lastly check whether the relevant status profile is assigned to the relevant objects.