on 02-24-2011 5:22 AM
Hi,
We have EWM 7.0 integrated with ECC 6.0.
When I Post Unplanned Goods Issue in EWM with GI process = SCRP (scrapping), I expect to post 551 movement in ECC.
However this doesn't happen.
On analyzing the inbound queue in ECC 6.0, it is found "reason code" is set as mandatory to post movement 551 in ECC.
Can any one tell how to send the reason code from EWM to ECC ?
Thankyou in advance.
Best regards
hi,
you need to check SAP note 1408478 for more detail how to send this reason code back to ERP.