Dear All

We are having no valuated WBS. We have Production Orders which are assigned with these WBS. Previously no planned cost are considered in WBS result analysis. But recently we found that in recently created production orders, system is considering the planned cost of production order in Result Analysis of WBS. In this case our material related costs get doubled as we also planned at WBS level for material cost..

Any idea what is the reason system is considering the planned cost of production order in WBS RA and how to restrict the same.

Thanks and Best Regards

Farhan Qaiser

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

In RA configuration you can define which costs are to be selected for RA run by maintaining the relevant Line ID's. You may discuss this with your CO consultant to get more clarity on this.

Regards,

Gokul

Former Member
0 Kudos

Hi Farhan,

In OPSV, just check if they have recently checked tick box 'Appended' for order type related to PP. This is responsible for adding planned costs of order to WBS.

Regards