on 02-23-2011 9:53 AM
Hi Qm Guru
My requirement is do source and GR inspection together.
For example: Once a material is inspected at vendor site and when the same material reaches to plant warehouse, then GR inspection is done.
How can we do these two inspections together?
Regards
Pooja
In standard SAP you can have one or another not both at the same time.
But you can use User exit to create multiple inspection lots. Which user exit to use will depend what it the trigger to create inspection lot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check out this link.
http://www.saptechies.com/how-to-do-source-inspection-in-qm/
Regards
Hari