Dear APO Expert,
I work with new Master data Created , Product and Location
PP Planning Procedure : IDES: Automatic planning immediately
I create new demand for Product P-100 at Distribution Center 2013
Production Plant at 2011
when i transfer Demand whether through /SAPAPO/MC90 or Mass Processing , I can't find any Orders created for this plan at 2011 or even PurRqs at 2013
How i can define source determination in this case ??
Please Advise
Rami
Hi Rami,
Check following things-:
1. Procurement type for product in distrubution center is F or X
2. There is tlane between DC and plant.
3. Demand released is within PPDS horizon.
4. As it is forcast requirement recheck configuration of planning procedure 3 whether event forcast requirement is included to run product heuristic or cover that requirement.
5. To confirm Whether this is because of planning procedure you can enter planning procedure 4 iand heuristic in product master and take planning run.
It seems to me that it is not source determination problem.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.